Project Duration
Stipulated Date of Commencement October 02 2019
Stipulated Date of Completion /
Likely Date of Completion
November 01 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 470,510.00
Awarded for ₹ 456,169.00

Project highlights

miscellaneous interior works.

 
Gallery Image
Contractors
M/S.Creation Interior Contractor
Gallery Image
Consultants
M/s. F P Project Management Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation and maintenance of Government Schools in the state of Goa – Package VIA (Salcete Taluka)

View Project
Similar Project

Infrastructure Works For Sanjay Centre For Special Education at Bogda, Vasco -SH:Fire safety and exit signages work

View Project
Similar Project

Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Dharbandora Taluka – Package IV (GPS Hauliwada, GPS Kalsai, GPS Camarconda, GPS Matoje, GPS Panaswada)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.