Project Duration
Stipulated Date of Commencement
October 02 2019
Stipulated Date of Completion /
Likely Date of Completion November 01 2019
Likely Date of Completion November 01 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 470,510.00
Awarded for
₹ 456,169.00
Project highlights
miscellaneous interior works.
Contractors
M/S.Creation Interior Contractor
Consultants
M/s. F P Project Management Pvt. Ltd.