Project Duration
Stipulated Date of Commencement
October 05 2018
Stipulated Date of Completion /
Likely Date of Completion March 04 2019
Likely Date of Completion March 04 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,439,186.00
Awarded for
₹ 19,999,179.84
Project highlights
External Development works
Contractors
M/s.Decent Decorators,
Consultants
M/s. F P Project Management Pvt. Ltd.
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Ponda Taluka: GPS Volvoi & GPS Veling
View Project
Infrastructure works for Sanjay Centre for Special Education at Porvorim
View Project
Look and Image Operations for the Lusofonia Games, Goa – 2014.
View Project





