Project Duration
Stipulated Date of Commencement
September 01 2006
Stipulated Date of Completion /
Likely Date of Completion April 01 2007
Likely Date of Completion April 01 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,777,629.00
Awarded for
₹ 1,798,714.00
Project highlights
The building consists of 2 classrooms, staff room, toilets, etc.
Contractors
M/s. Sharadchandra H. Katkar
Consultants
M/s. Effective Architectural Services
See Similar Projects
Reconstruction of school at GPS Bicholim (Central)
View Project
Repairs/Upgradation & Maintenance of Government schools in the State of Goa – Quepem Taluka – Package F.
View Project
Repairs/Upgradation of Government High School at Vadenagar,Vasco, Goa.
View Project





