Project Duration
Stipulated Date of Commencement April 10 2015
Stipulated Date of Completion /
Likely Date of Completion
July 09 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,184,374.00
Awarded for ₹ 16,708,003.14

Project highlights

Interior & Furniture works

 
Gallery Image
Contractors
M/s. Shalaka Infra Tech (I) Pvt. Ltd.
Gallery Image
Consultants
M/s. KICONS Limited
 
Similar Projects

See Similar Projects

Similar Project

Infrastructure works for Sanjay Centre for Special Education at Bogda, Vasco.

View Project
Similar Project

Repairs/Upgradation & maintenance of Government schools in the state of Goa – Tiswadi taluka – Package-I (GPS Dhulapi, GPS Mangoda, GPS Gawant, GPS Akhada)

View Project
Similar Project

Reconstruction of school at GPS Bicholim (Central)- Erection of 200KVA DTC along with the associated H.T UG Cable

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.