Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion October 22 2014
Likely Date of Completion October 22 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 89,455,485.00
Awarded for
₹ 105,345,058.70
Project highlights
Construction of Government College of Commerce & Economics, college building for Directorate of Higher Education.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. KICONS Limited
Sub Works
This project involved 2 sub works. The details of the same available below
1
Supply, Installation, Testing & Commissioning of CCTV & PA System
100% completed
Project Duration
Stipulated Date of Commencement
October 31 2016
Stipulated Date of Completion /
Likely Date of Completion November 29 2016
Likely Date of Completion November 29 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,904,203.00
Awarded for
₹ 1,649,951.00
Project highlights
CCTV & PA System
Contractors
M/s. Psytech Infosolutions Pvt. Ltd.
Consultants
M/s. KICONS Limited
2
Interior Furniture Works
100% completed
Project Duration
Stipulated Date of Commencement
April 10 2015
Stipulated Date of Completion /
Likely Date of Completion July 09 2015
Likely Date of Completion July 09 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,184,374.00
Awarded for
₹ 16,708,003.14
Project highlights
Interior & Furniture works
Contractors
M/s. Shalaka Infra Tech (I) Pvt. Ltd.
Consultants
M/s. KICONS Limited
See Similar Projects
Repairs/ Upgradation & Maintaince of Government schools in the State of Goa – Bardez Taluka-Package I – B
View Project
Construction of Government Primary School at Shantinagar – Pissurlem in Sattari Taluka.
View Project
Development of Government Village School Playground at Assonora in Bardez taluka (Assonora Sports Complex)
View Project