Project Duration
Stipulated Date of Commencement
November 17 2006
Stipulated Date of Completion /
Likely Date of Completion June 16 2007
Likely Date of Completion June 16 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,027,620.00
Awarded for
₹ 7,385,712.00
Contractors
M/s. Japsin Jacob Wire Drawing Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.