Project Duration
Stipulated Date of Commencement
January 13 2009
Stipulated Date of Completion /
Likely Date of Completion February 28 2009
Likely Date of Completion February 28 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 360,532.00
Awarded for
₹ 378,460.00