Project Duration
Stipulated Date of Commencement January 25 2007
Stipulated Date of Completion /
Likely Date of Completion
October 25 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 29,518,019.00
Awarded for ₹ 31,090,000.00
 
Gallery Image
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Maintenance Works of Goa Medical College and Hospital & Goa Dental College S.H.: Supply, Installation, Testing & Commissioning of 2 Nos. 5.5TR ductable units for MRI section at Goa Medical College, Bambolim-Goa.

View Project
Similar Project

Maintenance works of Goa Medical College and Hospital & Goa Dental College at Bambolim, Goa. SH – Carriage of water”

View Project
Similar Project

Supply, installation, testing and commissioning of 2 nos. of 30 KVA UPS

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.