Project Duration
Stipulated Date of Commencement
January 25 2007
Stipulated Date of Completion /
Likely Date of Completion October 25 2007
Likely Date of Completion October 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 29,518,019.00
Awarded for
₹ 31,090,000.00
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.