Project Duration
Stipulated Date of Commencement September 15 2011
Stipulated Date of Completion /
Likely Date of Completion
January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 44,92,891.00
Awarded for ₹ 4,693,205.00
 
Gallery Image
Contractors
M/s. Imperial Engineering Co.
Gallery Image
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Interior work for branch office of Directorate of Food and Drugs Administration in Old Collectorate building, Margao, Goa

View Project
Similar Project

Maintenance of building under DFDA, Bambolim,Goa – SH-Maintenance contract of 180 KVA DG set installed at DFDA, Bambolim for three years.

View Project
Similar Project

Renovation of Building of Directorate of Higher Education, Porvorim, Goa – Civil, Electrical, Lift, HVAC, Interior and Furniture work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.