Project Duration
Stipulated Date of Commencement
December 21 2007
Stipulated Date of Completion /
Likely Date of Completion June 20 2010
Likely Date of Completion June 20 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 573,453,985.00
Awarded for
₹ 734,634,449.00
Project highlights
Basement + Ground + 5 RCC framed structure
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.