Project Duration
Stipulated Date of Commencement
January 31 2019
Stipulated Date of Completion /
Likely Date of Completion October 09 2019
Likely Date of Completion October 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,648,356.00
Awarded for
₹ 5,334,598.46
Contractors
M/s.Sneh Vaibhav Enterprises
Consultants
M/s. Bhaskar Wagle and Associates.