Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion July 25 2007
Likely Date of Completion July 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,341,079.00
Awarded for
₹ 17,638,454.00
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
See Similar Projects
Upgradation of Infrastructure in Rural Areas Under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme, 2013 – Construction of Panchayat Ghar at V.P. Cavelossim.
View Project
Signages work
View Project
Landscaping work
View Project





