Project Duration
Stipulated Date of Commencement December 02 2010
Stipulated Date of Completion /
Likely Date of Completion
January 01 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,791,003.00
Awarded for ₹ 2,766,560.00
 
Gallery Image
Contractors
M/s. Accutech Power Solutions Pvt. Ltd.
Gallery Image
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Package I (Village Panchayat Agassaim, Village Panchayat Neura).

View Project
Similar Project

HVAC work.

View Project
Similar Project

Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Construction of Community Hall and Shops at V.P. Querim in Ponda Taluka..

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.