Project Duration
Stipulated Date of Commencement
November 10 2010
Stipulated Date of Completion /
Likely Date of Completion February 09 2011
Likely Date of Completion February 09 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,860,438.00
Awarded for
₹ 15,652,550.00
Contractors
M/s. Simca Aluminium Pvt. Ltd.
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.