Project Duration
Stipulated Date of Commencement
January 13 2011
Stipulated Date of Completion /
Likely Date of Completion February 12 2011
Likely Date of Completion February 12 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,680,000.00
Awarded for
₹ 1,680,000.00
Contractors
M/s. Mohansons India
Consultants
In-house (GSIDC)