Status
100%
Completed
 
Gallery Image
Contractors
Gallery Image
Consultants
 

Sub Works

This project involved 4 sub works. The details of the same available below

1

Phase I : Land Development.

100% completed
 
Project Duration
Stipulated Date of Completion /
Likely Date of Completion
June 02 2003
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,007,426.03
Awarded for ₹ 3,694,673.60

Project highlights

• Built-up area : 2670 sq. m.
• Construction of bus stand with amenities such as shops, cafeteria, wash rooms etc.
• Roof is designed as a wave supported by columns and trusses representing palm trees.
• Bus entries and exits are separate and independent from commuter entry.
• Floor height in the bays is aligned with the first step of the bus for easier access.
• Smooth traffic flow is ensured including that of taxis and rickshaws.
• Provision for taxi stand, motor cycle stand, rickshaw stand, etc.
• 10 nos. parking bays for scheduled buses. Besides there are bays for idle parking of buses.
• Parking for private vehicles.
• Rest room for passengers, drivers and staff.

 
Contractors
Contractors
M/s.Sunil Construction
Consultants
Consultants
M/s. Rahul Deshpande & Associates
2

Phase II

100% completed
 
Project Duration
Stipulated Date of Commencement January 27 2004
Stipulated Date of Completion /
Likely Date of Completion
July 27 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,989,680.00
Awarded for ₹ 28,751,965.00
 
Contractors
Contractors
M/s.D. S. Contractors Pvt. Ltd.
Consultants
Consultants
M/s. Rahul Deshpande & Associates
3

Landscaping work.

100% completed
 
Project Duration
Stipulated Date of Commencement May 05 2004
Stipulated Date of Completion /
Likely Date of Completion
May 25 2004
Status
100%
Completed
Cost (₹)
Awarded for ₹ 97,000.00
 
Contractors
Contractors
M/s. Hariyalee Nursery
Consultants
Consultants
M/s. Rahul Deshpande & Associates
4

Signages.

100% completed
 
Project Duration
Stipulated Date of Commencement May 05 2004
Stipulated Date of Completion /
Likely Date of Completion
May 25 2004
Status
100%
Completed
Cost (₹)
Awarded for ₹ 133,883.00
 
Contractors
Contractors
M/s. Home Deco
Consultants
Consultants
M/s. Rahul Deshpande & Associates
Similar Projects

See Similar Projects

Similar Project

Construction over bridge at Valvanti river connecting Bhandarwada to Vithalapur Sankhali.

View Project
Similar Project

Dismantling of HT overhead lines and supplying & laying of HT Underground cables at Panjim – HT Cable work from EDC Substation to Chimbel junction – Additional Work

View Project
Similar Project

Comprehensive electrical underground cabling work at Bambolim.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.