Project Duration
Stipulated Date of Commencement
October 29 2008
Stipulated Date of Completion /
Likely Date of Completion December 28 2009
Likely Date of Completion December 28 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,898,627.00
Awarded for
₹ 5,597,315.90
Contractors
M/s. Mohan Electricals
Consultants
M/s. Vijaykumar Sawant Associates