Project Duration
Stipulated Date of Commencement
February 27 2012
Stipulated Date of Completion /
Likely Date of Completion June 26 2012
Likely Date of Completion June 26 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,417,128.15
Awarded for
₹ 20,297,433.80
Contractors
M/s. Steel Case
Consultants
M/s. Effective Architectural Services