Project Duration
Stipulated Date of Commencement October 23 2012
Stipulated Date of Completion /
Likely Date of Completion
November 02 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,383,028.75
Awarded for ₹ 22,999,093.20

Project highlights

The RCC Simply supported Bridge is (Approx.) 35m in length comprising of 02 spans (approx. 17mts) supported by a central pier and on two abutment walls on both banks of the rivulet. •
The total length of approach roads is approx 400mts.

 
Gallery Image
Contractors
M/s. Indiana Build Infrastructure Pvt. Ltd.
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates (PMC)
 
Similar Projects

See Similar Projects

Similar Project

Construction of Pedestrian Arch Bridge connecting Mandovi River Promenade and DB Road, over St. Inez Creek near ESG Building at Panaji

View Project
Similar Project

Construction of Road Bridge at Balli in Quepem Constituency on Balli – Fatorpa MDR Road at Balli in Quepem.

View Project
Similar Project

Construction of Bus Stand & Mini Depot at Sankhali, Goa. – Balance works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.