Project Duration
Stipulated Date of Commencement October 23 2012
Stipulated Date of Completion /
Likely Date of Completion
November 02 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,383,028.75
Awarded for ₹ 22,999,093.20

Project highlights

The RCC Simply supported Bridge is (Approx.) 35m in length comprising of 02 spans (approx. 17mts) supported by a central pier and on two abutment walls on both banks of the rivulet. •
The total length of approach roads is approx 400mts.

 
Gallery Image
Contractors
M/s. Indiana Build Infrastructure Pvt. Ltd.
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates (PMC)
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of the Road connecting Integrated School Complex to NH17 – Civil, Plumbing & Electrical works

View Project
Similar Project

Demolition Of Existing Bridge And Reconstruction Of Box Culvert On 18th June Road Over St. Inez Creek, Panaji -Illumination Work

View Project
Similar Project

Hot mixing and Improvement of Internal Roads in V. P. Dramapur, Sirlim in Velim Constituency.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.