Project Duration
Stipulated Date of Commencement April 15 2022
Stipulated Date of Completion /
Likely Date of Completion
December 14 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 32,678,364.00
Awarded for ₹ 36,058,328.56

Project highlights

Development of parking space

 
Gallery Image
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. KICONS Limited
 
Similar Projects

See Similar Projects

Similar Project

Full renovation and part construction of the old Asilo Hospital for State Health Training Institute at Mapusa-SH-Interior works.

View Project
Similar Project

Civil, Plumbing, Electrical, Lift & Fire – Fighting works – Balance works

View Project
Similar Project

Supply, Installation, Testing and Commissioning of negative pressure VRDL lab at Goa Medical College and Hospital, Bambolim.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.