Project Duration
Stipulated Date of Commencement October 26 2006
Stipulated Date of Completion /
Likely Date of Completion
February 25 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 15,119,623.00
Awarded for ₹ 11,376,000.00
 
Gallery Image
Contractors
M/s. BOC India Limited
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Maintenance of 200 KVA transformer installed at Primary Health Centre, Pillem Dharbandora (PHC Tisk)

View Project
Similar Project

Demolition and reconstruction of 220 bedded hospital in place of Public Health Center – (I. D. Hospital) at Sadar Ponda Goa.

View Project
Similar Project

Upgradation of Primary Health Centre at Shiroda, Goa – Civil, Plumbing, Electrical, Elevators, Fire Fighting and Landscaping works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.