Project Duration
Stipulated Date of Commencement
March 21 2013
Stipulated Date of Completion /
Likely Date of Completion June 20 2013
Likely Date of Completion June 20 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 853,639.00
Awarded for
₹ 840,171.60
Contractors
M/s.Rakesh Kambli
Consultants
In-house (GSIDC)