Project Duration
Stipulated Date of Commencement November 05 2014
Stipulated Date of Completion /
Likely Date of Completion
May 04 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 292,919,099.00
Awarded for ₹ 357,020,022.60

Project highlights

New building for the CHC with 80 bed capacity

 
Gallery Image
Contractors
M/s. MVR Infra Projects Pvt. Ltd
Gallery Image
Consultants
M/s. Saolapurkar and Associates
 
Similar Projects

See Similar Projects

Similar Project

Soft landscaping of area around OPD, Casualty, Ward Block & Courtyards at GMC, Bambolim, Goa.

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Cardiac Monitors, ECG machine, Defribrillators, etc.

View Project
Similar Project

Maintenance of hospitals CHC’s, PHC’s, RMD’s under Directorate of Health services S.H Maintenance of Split & window Air conditioning units at various location in the state of Goa for a period of 3 years.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.