Project Duration
Stipulated Date of Commencement
November 05 2014
Stipulated Date of Completion /
Likely Date of Completion May 04 2016
Likely Date of Completion May 04 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 292,919,099.00
Awarded for
₹ 357,020,022.60
Project highlights
New building for the CHC with 80 bed capacity
Contractors
M/s. MVR Infra Projects Pvt. Ltd
Consultants
M/s. Saolapurkar and Associates
See Similar Projects
– Hospital Furniture
View Project
Updating the work of provision of fire safety measures at Goa Medical College and Goa Dental College, Bambolim, Goa. -Civil works.
View Project
Interior and Furniture works
View Project





