Project Duration
Stipulated Date of Commencement
June 21 2013
Stipulated Date of Completion /
Likely Date of Completion October 20 2013
Likely Date of Completion October 20 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,303,755.00
Awarded for
₹ 19,478,345.85
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Gurudutt Sanzgiri