Project Duration
Stipulated Date of Commencement February 07 2015
Stipulated Date of Completion /
Likely Date of Completion
February 06 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 73,480,851.00
Awarded for ₹ 97,176,913.14

Project highlights

Civil, Plumbing, Electrical, Lift & Fire – Fighting works.
1. The total bed capacity is 42.
2.The ground floor of the building shall have Casualty, 8 OPD’s & other rooms.
3.The first floor of the building shall have Operation theatre, Recovery room, etc.

 
Gallery Image
Contractors
M/s. shilpi Constructions
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of 2 nos. of 30 KVA UPS

View Project
Similar Project

Supply & Installation of Lead Doors & Lead Glass

View Project
Similar Project

Electrical works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.