Project Duration
Stipulated Date of Commencement
December 06 2020
Stipulated Date of Completion /
Likely Date of Completion March 05 2023
Likely Date of Completion March 05 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,363,835.00
Awarded for
₹ 7,155,597.00
Project highlights
Laying of water supply pieline for new high Court Complex from Atal Setu approach near Hero Showroom.
Contractors
M/s. Wibro Construction Co. Pvt. Ltd.,
Consultants
M/s LKS India Pvt. Ltd.
See Similar Projects
Construction of High Court Complex at Penha de Franca, Porvorim.
View Project
Construction of rumbler strips (4 in no.) and traffic signboards near Goa Institute of Management, Ribandar.
View Project
Providing 11 kV transformer substation for release of electrical connection to the office premises of at Vasco.
View Project





