Project Duration
Stipulated Date of Commencement
March 15 2008
Stipulated Date of Completion /
Likely Date of Completion March 14 2009
Likely Date of Completion March 14 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 40,071,151.00
Awarded for
₹ 63,000,000.00
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd.
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.