Project Duration
Stipulated Date of Commencement
June 16 2011
Stipulated Date of Completion /
Likely Date of Completion September 15 2011
Likely Date of Completion September 15 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,817,618.00
Awarded for
₹ 4,797,750.00
Project highlights
Providing and fixing of hand painted tiles cladding for the seating provided on the Main road.
Contractors
M/s. Shilpi Constructions
Consultants
M/s. Vijaykumar Sawant Associates