Project Duration
Stipulated Date of Commencement
July 03 2010
Stipulated Date of Completion /
Likely Date of Completion October 02 2010
Likely Date of Completion October 02 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,268,800.00
Awarded for
₹ 2,741,000.00
Contractors
M/s. James Electrical
Consultants
M/s. Vijaykumar Sawant Associates
See Similar Projects
Upgradation of infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme : Construction of Panchayat Ghar and Community Complex at V.P.Menkurem-Dhumashe.
View Project
Construction of New Panchayat Ghar for Village Panchayat at Siridao-Palem in the Survey no. 40/0 in the Village Siridao, Tiswadi
View Project
Public works in Calangute Constituency.
View Project