Project Duration
Stipulated Date of Commencement July 03 2010
Stipulated Date of Completion /
Likely Date of Completion
October 02 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,268,800.00
Awarded for ₹ 2,741,000.00
 
Gallery Image
Contractors
M/s. James Electrical
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates
 
Similar Projects

See Similar Projects

Similar Project

Online UPS System.

View Project
Similar Project

Construction of Community Hall in the Morlem Rehabilitation Colony in Sattari Taluka

View Project
Similar Project

Structural & Architectural work.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.