Project Duration
Stipulated Date of Commencement
February 09 2023
Stipulated Date of Completion /
Likely Date of Completion April 18 2023
Likely Date of Completion April 18 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,327,696.00
Awarded for
₹ 1,327,777.00
Project highlights
Alteration & Interior works
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Rajesh Kenkre