Project Duration
Stipulated Date of Commencement
May 18 2004
Stipulated Date of Completion /
Likely Date of Completion November 18 2004
Likely Date of Completion November 18 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,556,000.00
Awarded for
₹ 4,348,364.00
Project highlights
The work involved renovations and alterations to the existing ground floor of Foyer Block. Addition of units such as canteen, pharmacy, STD room, ATM room, Radiology room, Sonography room, blood sample collection room etc. it also includes construction of connecting corridor (Ground plus two) between the Foyer Block and Blood Bank.
Contractors
M/s. Midland Realtors Pvt. Ltd.,
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd