Project Duration
Stipulated Date of Commencement
August 04 2023
Stipulated Date of Completion /
Likely Date of Completion August 03 2024
Likely Date of Completion August 03 2024
Status
60%
Completed
Cost (₹)
Estimated at
₹ 41,600,623.00
Awarded for
₹ 40,526,955.80
Project highlights
Construction of security cabin, security towes, facility management block, store room, alteration of Asst. Solicitor cabin, interior work etc.
Contractors
M/s R. Z. Malpani
Consultants
M/s LKS India Pvt. Ltd.
See Similar Projects
Repairs/ Maintenance of Government Hospitals/ Health Centres under Directorate of Health Services SH : Elevator maintenance at Primary Health Centre, Bicholim for five years
View Project
Construction of New District & Sessions Court Complex at Merces, Tiswadi – Goa: Audio Video system.
View Project
Repairs/ Maintenance of Buildings under Directorate of Food and Drugs Administration, Bambolim – Goa. S.H. –Maintenance Contract for the 180kVA Diesel Generator set installed at Directorate of Food and Drugs Administration, Bambolim for three years (2021-2024)
View Project