Project Duration
Stipulated Date of Commencement
October 25 2013
Stipulated Date of Completion /
Likely Date of Completion December 08 2013
Likely Date of Completion December 08 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,873,194.00
Awarded for
₹ 5,696,228.64
Project highlights
Additional Electrical works required for completion of project
Contractors
M/s. Power & Instrumentation (Guj.) Ltd.
Consultants
In-house (GSIDC)