Project Duration
Stipulated Date of Commencement
April 19 2013
Stipulated Date of Completion /
Likely Date of Completion June 18 2013
Likely Date of Completion June 18 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,655,969.78
Awarded for
₹ 2,467,550.00
Project highlights
Additional Electrical works required for completing of project
Contractors
M/s. Arken Solutions Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
HVAC work.
View Project
Demolition and reconstruction of Market Complex at Bhoma Adcolna Panchayat Banastarim Goa -Civil, Plumbing, Electrical, HVAC, Lifts and Fire Fighting works
View Project
Upgradation of Infrastructure in Rural Areas Under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme, 2013 – Construction of Panchayat Ghar at V.P. Cavelossim.
View Project