Project Duration
Stipulated Date of Commencement
February 26 2015
Stipulated Date of Completion /
Likely Date of Completion April 06 2015
Likely Date of Completion April 06 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,508,891.00
Awarded for
₹ 2,984,637.00
Contractors
M/S. Power Engineering (India) Pvt Ltd
Consultants
In-house (GSIDC)