Project Duration
Stipulated Date of Commencement
August 26 2014
Stipulated Date of Completion /
Likely Date of Completion September 25 2014
Likely Date of Completion September 25 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 956,044.59
Awarded for
₹ 966,095.00
Contractors
M/s. Reconnoitre Systems
Consultants
In-house (GSIDC)