प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख January 2 2016
पूर्ण होण्याची वास्तविक तारीख June 30 2022
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 151141272.59
ला देण्यात आला ₹ 157912311.00
प्रकल्पाची अंतिम किंमत ₹ 107022086.00

प्रकल्पाची ठळक वैशिष्ट्ये

The work of Promenade was executed from Youth Hostel to Kala Academy having 900 meter length with 4.5 m wide walkway & 2.5 m cycle track. Rip rap was provided to protect the coast. Selfie points & senior citizen park was renovated.

 
Gallery Image
कंत्राटदार
M/s. Krishna Builder
Gallery Image
सल्लागार
M/s. LKS India Pvt Ltd.
 
Similar Projects

यासारखे प्रकल्प बघा

Similar Project

Testing & Commissioning of the fire Fighting, Fire Alarm and PA System

तपशील पहा
Similar Project

Modular Furniture works

तपशील पहा
Similar Project

Installation and maintenance of chemical portable toilets for Exposition of St. Francis Xavier 2014 – 2015 at Old Goa.

तपशील पहा
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
अस्वीकरण: राजभाषा संचालनालय, गोवा सरकार द्वारे अनुवादित. टीप: कोणत्याही परिस्थितीत कायदेशीर अर्थाविष्कारासाठी, इंग्रजी आवृत्तीला प्राधान्य दिले जाईल.