Project Duration
Stipulated Date of Commencement
January 2 2016
Actual Date of Completion
June 30 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 151141272.59
Awarded for
₹ 157912311.00
Final Cost of Project
₹ 107022086.00
Project highlights
The work of Promenade was executed from Youth Hostel to Kala Academy having 900 meter length with 4.5 m wide walkway & 2.5 m cycle track. Rip rap was provided to protect the coast. Selfie points & senior citizen park was renovated.