Project Duration
Stipulated Date of Commencement
October 04 2021
Stipulated Date of Completion /
Likely Date of Completion July 03 2022
Likely Date of Completion July 03 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,598,613.23
Awarded for
₹ 28,794,751.15
Project highlights
At present Cumbarjua farmers having fields in Jua Village have to cross water tributary from Cumbarjua to Jua Village to access their fields. Proposed bridge will fulfill the long-standing demand of the farmers to access their fields. The bridge will cater to foot traffic and tractor movement.
Construction of Bridge of total length of 50 mtrs. , Carriage way of 3 mtrs, to provide single lane for tractor traffic.
Contractors
M/s. KVJ Builders and Developers
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Construction of single lane bridge in village Dongrim, Village Panchayat Azzosim Mandur – Approach road work
View Project
SH: Supply of 5 numbers of 20 ft X 30 ft Indian National Flag
View Project
Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) :-Civil works.
View Project