Project Duration
Stipulated Date of Commencement
December 18 2021
Stipulated Date of Completion /
Likely Date of Completion December 17 2022
Likely Date of Completion December 17 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 88,233,685.00
Awarded for
₹ 94,759,752.11
Project highlights
Construction of Community hall, football ground and stadium and futsal ground
Contractors
M/s R. Z. Malpani
Consultants
M/s. Keni D’Souza