Project Duration
Stipulated Date of Commencement
March 15 2024
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
5%
Completed
Cost (₹)
Estimated at
₹ 50,241,030.04
Awarded for
₹ 52,722,392.44
Project highlights
Interior , Furniture Works
Contractors
M/s. Parnika Commercial & Estates P. Ltd
Consultants
M/s. KICONS Limited