Project Duration
Stipulated Date of Commencement
December 26 2023
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
51%
Completed
Cost (₹)
Estimated at
₹ 26,524,126.58
Awarded for
₹ 28,457,026.40
Project highlights
Electrical and LV works of the building.
Contractors
M/s. Siddharud Electricals
Consultants
M/s. KICONS Limited
See Similar Projects
Balance HVAC works.
View Project
Upgradation of NICO at Goa Medical College, Bambolim at Goa- Supply, Installation, Testing and Commissioning of DG Set.
View Project
Supply, Installation, Testing and Commissioning of 100KLD Sewage Treatment Plant and allied Civil works.
View Project