Project Duration
Stipulated Date of Commencement
October 28 2021
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
95%
Completed
Cost (₹)
Estimated at
₹ 134,712,342.12
Awarded for
₹ 151,930,381.32
Project highlights
Expansion of existing Primary Health Centre, Sanguem by constructing new 44 bedded Hospital.
Contractors
M/s. DHIPL Projects Pvt. Ltd.
Consultants
M/s. KICONS Limited
See Similar Projects
Setting up of 50 Bedded Integrated AYUSH Hospital at South Goa, T.B. Hospital premises, Margao, Salcete – Goa – Civil, Plumbing, Electrical, Lift, HVAC and Fire Fighting works
View Project
Construction of 50 bedded Integrated AYUSH Hospital at Velguem.
View Project
Construction of Hospital at Bicholim for Deendayal Janaseva Pratisthan Trust under CSR Funds of Indian Oil Corporation Ltd.
View Project