Project Duration
Stipulated Date of Commencement
June 04 2021
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
72%
Completed
Cost (₹)
Estimated at
₹ 131,936,242.10
Awarded for
₹ 118,728,277.36
Project highlights
Construction of 50 bedded
integrated AYUSH Hospital in South Goa
Contractors
M/s Bishan Infrastucture Pvt. Ltd
Consultants
M/s. Datta Kare Associates