Project Duration
Stipulated Date of Commencement September 22 2015
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
85%
Completed
Cost (₹)
Estimated at ₹ 167,103,404.00
Awarded for ₹ 196,795,091.44

Project highlights

The scope includes renovation of Existing Ravindra Bhavan at Curchorem and Construction of IInd Phase of Ravindra Bhavan which include the following:-
• New auditorium of 200 seats
• Amphitheatre of 2000 Capacity
• Statue of Gurudev Ravindranath Tagore
• Guest Rooms
• Administrative offices & Conference Room
• Sound insulated Musical Classes / Workshops
• Convenience shops
• Utility structures
• Site Development

 
Gallery Image
Contractors
M/s. AYG Realty Pvt. Ltd
Gallery Image
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
 

Sub Works

This project involved 6 sub works. The details of the same available below

1

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Interior and Allied Works

20% completed
 
Project Duration
Stipulated Date of Commencement March 06 2024
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
20%
Completed
Cost (₹)
Estimated at ₹ 18,534,545.98
Awarded for ₹ 26,275,688.00

Project highlights

The scope of work includes Acoustic Wall panaelling, Acoustic False ceiling, signages, Furniture works, aluminium louvers, etc.

 
Contractors
Contractors
M/s. Deshpande Constructions
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
2

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Road and Misc. Works

30% completed
 
Project Duration
Stipulated Date of Commencement April 18 2022
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
30%
Completed
Cost (₹)
Estimated at ₹ 11,680,980.00
Awarded for ₹ 12,055,767.00

Project highlights

The scope of work includes construction of Concrete road, laying of pavers, etc.

 
Contractors
Contractors
M/s. A.R. Constructions
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
3

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Stage lighting and Drapery works

35% completed
 
Project Duration
Stipulated Date of Commencement October 21 2021
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
35%
Completed
Cost (₹)
Estimated at ₹ 4,451,677.00
Awarded for ₹ 3,499,308.00

Project highlights

The scope of work includes stagelighting and drapery system for Auditorium.

 
Contractors
Contractors
M/s. Canara Lighting Industries Pvt. Ltd
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
4

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa .-CCTV works

15% completed
 
Project Duration
Stipulated Date of Commencement October 29 2021
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
15%
Completed
Cost (₹)
Estimated at ₹ 1,117,943.00
Awarded for ₹ 1,066,970.00

Project highlights

The scope of work includes CCTV cameras for Amphitheatre , Auditorium and Surrounding premises.

 
Contractors
Contractors
M/s. Geeta Automation and Technologies
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
5

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa.- Audio Video (AV) Works.

30% completed
 
Project Duration
Stipulated Date of Commencement August 30 2022
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
30%
Completed
Cost (₹)
Estimated at ₹ 12,340,311.00
Awarded for ₹ 11,927,174.00

Project highlights

Audio Video (AV) Works.

 
Contractors
Contractors
M/s. Pentagon Automation Concepts
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
6

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa.- 11 KV HT Substation Work.

20% completed
 
Project Duration
Stipulated Date of Commencement February 26 2024
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
20%
Completed
Cost (₹)
Estimated at ₹ 19,286,229.92
Awarded for ₹ 19,187,318.28

Project highlights

HT Power supply to the premises.

 
Contractors
Contractors
M/s. Siddharud Electricals
Consultants
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
Similar Projects

See Similar Projects

Similar Project

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Road and Misc. Works

View Project
Similar Project

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Stage lighting and Drapery works

View Project
Similar Project

Construction of Modern Fire Station at Bicholim, Goa – Balance works (2nd Call)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.