Project Duration
Stipulated Date of Commencement November 01 2018
Stipulated Date of Completion /
Likely Date of Completion
January 31 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,242,623.00
Awarded for ₹ 5,949,043.80

Project highlights

Construction of foundation for installtion of shinohara offset printing machine procured by the department. The premises of machine area is renovated and is equipped with HVAC as per machine requirment for dust free environment.

 
Gallery Image
Contractors
M/s.Kamat Equipment Services
Gallery Image
Consultants
M/s.Rajesh Kenkre
 
Similar Projects

See Similar Projects

Similar Project

Construction of Office Building for Directorate of Accounts at Porvorim, Goa – Interior and Other Miscellaneous Works

View Project
Similar Project

Construction of Laboratories for Agricultural Department at Ella Old Goa and Margao.

View Project
Similar Project

Construction of compound wall at Calangute / Saligao in North Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.