Project Duration
Stipulated Date of Commencement
January 24 2014
Stipulated Date of Completion /
Likely Date of Completion July 23 2014
Likely Date of Completion July 23 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 48,097,756.00
Awarded for
₹ 54,788,911.15
Project highlights
· The project includes Construction of Jogger’s Park in a plot of Area 30821 Sqm located at Dabolim, Mormugao Taluka at South Goa District.
Contractors
M/s. Girish Enterprises Pvt. Ltd.
Consultants
M/s. Casta Engineers Pvt. Ltd.
See Similar Projects
Construction of Library Building at Margao.
View Project
Upgradation of infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme 2013 – Reconstruction of Panchayat building at V.P.Honda.
View Project
Beautification of Valpoi Town.
View Project





