Project Duration
Stipulated Date of Commencement
October 22 2020
Stipulated Date of Completion /
Likely Date of Completion February 01 2021
Likely Date of Completion February 01 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,974,090.44
Awarded for
₹ 2,449,069.00
Contractors
M/s. Creation Interior Contractors
Consultants
M/s. FP Project Management