Project Duration
Stipulated Date of Commencement
February 19 2010
Stipulated Date of Completion /
Likely Date of Completion June 18 2010
Likely Date of Completion June 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 691,420.00
Awarded for
₹ 792,560.00
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Effective Architectural Services